Pre-Feasibility Logistics for Critical Minerals
Independent pre-feasibility logistics research found two routes prior advisors had missed and informed a US$25M commitment on deadline.
Read the case studyThe Question
Case study · Mining · Multi-site planning
Client's brief · reconstructed excerpt · values held in confidence
A multi-site gold producer runs four mines in (withheld), South America: open-pit and underground operations, a seasonally constrained site, and an oxide processing operation under strict TOC limits. Budget season is close, the board keeps asking questions leadership can't answer with confidence, and a fleet allocation capex decision worth (withheld) is approaching without a defensible basis. A previous consultant's model was harder to understand than the problem, and the in-house statistician's Excel workarounds take a week to run. The VP of Continuous Improvement needs answers across all four mines before the (withheld) board meeting, on a budget that rules out four separate models.
Bars cover values SimWell holds and is not releasing. The released figures stand as printed.
§ 1
In late 2024, a multi-site gold producer operating four Gold mines in South America was heading into budget season with a problem nobody could fully explain. The operation had a plan. It also had a pattern: execution kept slipping into reactive mode, the board kept asking questions leadership couldn't answer with confidence, and a capex decision on fleet allocation was approaching without a defensible basis for making it.
A previous consultant had already tried to help. The model they delivered was harder to understand than the original problem. The client's own statistician built Excel workarounds to fill the gap, but those took a week to run and produced results that were still difficult to stand behind in front of a board. The VP of Continuous Improvement needed answers across four operationally distinct mines, under a hard deadline, with a budget that ruled out four separate models.
The four mines were distinct in the ways that matter. Open-pit and underground operations ran across development headings with variable haul profiles, while the oxide processing operation operated under strict TOC limits that directly governed crusher feed quality. The throughput of the haulage and crushing operations was determined by the movement of material upstream. The seasonally constrained operation could not deploy certain fleets during the MASA rainy period, making quarterly output targets genuinely uncertain. Each site had its own planning complexity, and none of the existing tools could represent how those complexities interacted across the portfolio.
§ 2
Is this four problems, or one system with four configurations?
How most firms approach it. The default path is to scope each mine separately. Clients rarely present a portfolio problem. They present four mine problems, and consultants respond to the brief as given. Separate scopes contain risk. If one model fails, the others are unaffected, and four independent deliverables are easier to manage, price, and hand off. The result is four models with four rule sets that diverge the moment the engagement ends.
What SimWell proposed instead. Before writing a line of code, SimWell stepped back to ask whether the four mines were actually four distinct problems or variations of a single system. They were variations. Same mill chain. Same material flow logic. Same core planning constraints with site-specific parameters. SimWell proposed a single, parameterized architecture: core logic built once, each mine configured through an input scenario manager. Switching between mines meant changing inputs, not rebuilding models.
“If you plan ahead and find the similarities across all of them, it's the natural solution. People don't do it because they don't plan. They just start doing it.”
Mary Klincevicius, Solution Owner, SimWell
§ 3
The unified AnyLogic model represented the full mine-to-mill chain across all four operations: block sequencing, equipment availability, MASA wet-season constraints, ROM pad blending with TOC enforcement, grade blending recalculated every 50 cycles, and continuous plant modeling through the crusher, mill, and leach. All scenario inputs were exposed through the scenario manager so client engineers could run analyses without SimWell involvement. The model ran on a one-year horizon, matching the board and capex cadence it was built to support. The board discussion was grounded in how the system actually behaved over twelve months, not how averages suggested it should.
What the model revealed
Cleared for release
The model changed what leadership could see. It also changed what they could do.
Operations that plan in spreadsheets and execute in reactive mode often discover that the gap is structural. Simulation makes that gap visible before it shows up in production. SimWell works with mining operations teams to build that visibility, and to leave the capability inside the organization when the engagement ends.
More case studies
Independent pre-feasibility logistics research found two routes prior advisors had missed and informed a US$25M commitment on deadline.
Read the case studyA sulfur logistics model found the real constraint two stations upstream of where every operations team was pointing and redirected a capex decision worth hundreds of millions.
Read the case studyA simulation-based planning environment gave a vertically integrated manufacturer a multi-year planning horizon, up from three months, with feasibility answers inside a 30-minute meeting.
Read the case studyWant to learn more? Subscribe to our newsletter for the latest updates and industry news.